Configuring release planning information

If you use folders to track items, you may want to include information about the time and users available to work on an upcoming release, iteration, or project. This can help you estimate and calculate the man hours required to complete work in a specified time period. If you use Agile, you can indicate the number of target story points for an iteration.

As you enter release planning information, calculations are automatically performed to determine the number of available man hours. The resulting information is displayed in the Release Planning pane in the Folders list window and is automatically updated as work progresses. See Using the Folders list window

Note: The Release Planning pane in the Folders list window and the Release Planning tab in the Add Folder and Edit Folder dialog boxes are only available if the Enable Release Planning fields option is selected for the folder type. See Adding folder types.

1. Click the Release Planning tab when you are adding or editing a folder.

2. Select a Start date and End date for the release.

3. Select Include weekends to include Saturday and Sunday in the total number of working days for the specified period.

4. Enter the number of holidays and other non-working days that apply to all users working on the release.

This value is subtracted from the working days in the specified period.

5. Enter the number of working hours in day.

This value supports up to two decimal places. The working days in the period (adjusted) value is multiplied by this value to determine the number of working hours in period.

6. Enter the number of users available to work on the release.

This value supports up to two decimal places. The working hours in period value is multiplied by this value to determine the number of available man hours.

7. Enter the number of vacation and sick days in hours.

This value supports up to two decimal places. This value is subtracted from the man hours in period value to determine the final available man hours value.

8. Enter the Target story points to indicate the story points to complete during the specified period.

Story points are a relative unit of measurement used in Agile to estimate the difficulty or complexity of an item. Leave the value set to 0 if you do not use Agile or if you do not want to use story points.

9. Click OK to save the changes.

 